Dhaka Elevated Expressway’s Panthakunja Ramp: Construction Nears Completion Despite Challenges

The Panthakunja ramp of the Dhaka Elevated Expressway will add a new dimension to Dhaka’s transport system. People involved in the project hope the ramp will make the expressway work even better once it opens after long construction problems and many challenges. The ramp will make road travel easier in several important areas of the capital. Officials have also taken steps to redo the Panthakunja area and make it clean and well decorated.
Meanwhile, another inter ministry meeting decided how to finish the project work quickly. The decisions cover coordination among various agencies, shifting utility lines and removing construction problems. So finishing the work on Panthakunja and the rest of the expressway has gained fresh importance. The meeting stressed removing the obstacles in the way of the project. It also gave importance to lowering the height of a transfer station in Panthakunja Park and reopening the mouth of a box culvert to build the ramp. The meeting also asked the agencies concerned to take the needed steps to shift the WASA water line from Banglamotor to Katabon. It asked them to do the same for the power line from Banglamotor to Palashi.
Mr. Mohammad Abdur Rouf is Secretary of the Bridges Division and executive director of the Bangladesh Bridge Authority. He told Inqilab that they face some challenges in building the ramp near Panthakunja Park on the Dhaka Elevated Expressway. He said he hopes to overcome these challenges and open the ramp to traffic soon. He said they are working fast with the aim of finishing the construction by December and opening it to traffic. He said officials asked the Chinese delegation and others concerned to take the needed steps to finish the up ramp near Panthakunja Park by December and open it to traffic. They also stressed finishing the rest of the project quickly. He said they work to make sure Dhaka residents get the benefits of the project very soon.
People involved in the project say that, as of last September, physical work was 99.94 percent done in the first phase, 87.03 percent in the second phase and 22.45 percent in the third phase. The overall physical progress of the project is 80.72 percent. Building one ramp is not the only focus. Officials also give importance to turning the Panthakunja area into a planned and attractive place. After construction ends, they will take steps as needed to beautify the area, improve the travel environment and restore order to the infrastructure. This will help expressway users. It will also make the area better organized for local residents and pedestrians.
The project runs up to Kutubkhali on the Dhaka Chattogram highway. Its aim is to reduce the traffic load on the city’s inner roads and make fast travel possible. To get the full benefit of the project, it is urgent to connect its parts and open the ramps. So they see the Panthakunja ramp as an important link.
Panthakunja sits in a very important area of the capital. It connects with Banglamotor, Karwan Bazar, Hatirjheel, Moghbazar, Palashi and Shahbagh. Countless private cars, public transport, motorcycles, rickshaws and other vehicles use these roads every day. Once the Panthakunja ramp opens, the expressway will connect better with the important roads around it. Officials are taking steps to make the Panthakunja area beautiful, clean and orderly. They give importance to rebuilding the area and clearing the mess that construction has caused.
Environmental concerns, protests, court orders and many debates over the construction have caused long delays in this part of the project. Environmentalists and urban planners especially objected to building the ramp on land from Panthakunja Park.
Mr. Kofil Uddin works in the Karwan Bazar area. He told Inqilab that a very large number of people move around Karwan Bazar, Panthakunja, Banglamotor and nearby areas every day. The area has residential buildings, offices, businesses, hospitals and many important sites. So road transport here directly affects the lives of local people. He said that once the elevated expressway ramp here is finished, local residents and workers will travel easily. But he said officials must ensure safe space for pedestrians and the use of footpaths. They must also stop cars parking anywhere.