More Than 100,000 People Suffer for Two Decades
Tk 6 Crore Kaukhali Health Complex Remains Incomplete, Leaving People in Suffering for Two Decades

More than 100,000 people in the region have been deprived of proper healthcare for nearly two decades due to the failure to construct a new building at Kaukhali Upazila Health Complex in Pirojpur.
After a project remained stalled for years due to various irregularities and corruption, the Health Engineering Department (HED) recently issued a work order to construct a temporary building within 45 days following demands from local residents. However, even after seven months, the work remains incomplete, leaving patients in severe hardship while seeking medical treatment.
According to local residents and case records, the Health Engineering Department declared the main building of Kaukhali Health Complex risky around 18 years ago. Later, in 2008, the department awarded a contract through a tender to a Barishal-based construction firm, Messrs Noori Enterprise, to build a three-storey hospital building at a cost of around Tk 6 crore.
Under a project to upgrade the hospital from 31 to 50 beds, an outpatient department (OPD) building and two residential buildings were supposed to be constructed. Although the agreement was signed on June 25, 2008, and the work was scheduled for completion by February 2010, the contractor failed to finish the project.
Allegations have surfaced that Noori Enterprise resorted to various irregularities and corruption from the beginning of the project. The contractor allegedly took additional money after completing only part of the work.
Later, the contractor abandoned the project without completing it, resulting in the wastage of public funds. The building was never put to use. Subsequently, the Anti-Corruption Commission (ACC) filed a case over the alleged irregularities.
Although tenders were floated twice for the construction of a new hospital building over the years, the project remained stalled for unknown reasons. Eventually, amid severe public suffering and demands from local residents, the authorities took the initiative to construct a temporary facility as an alternative.
According to a work order dated May 5, 2026, signed by Tanjila Ferdousi, Executive Engineer of the Health Engineering Department’s Pirojpur Division (Memo No. 45.02.0079.363.18.001.26-343), the contracting firm Messrs Howlader Foundation was assigned to construct a single-storey semi-permanent structure for the OPD and kitchen blocks at Kaukhali Upazila Health Complex.
The contract was worth more than Tk 1.11 crore. Under its terms, the contractor was required to take possession of the site within seven days of signing the agreement and complete and hand over the project within 45 days.
However, despite the strict deadline, the construction of the temporary facility remains incomplete even after seven months. As a result, residents of Kaukhali continue to suffer from the longstanding shortage of healthcare facilities. Local residents have demanded that the authorities complete the construction work immediately to ease public suffering.
At the time, Upazila Health and Family Planning Officer Dr. Subrata Karmakar said the shortage of buildings was disrupting healthcare services. There were also no residential facilities for doctors, nurses and other staff members.
However, he said the number of beds at the health complex had been increased and there were no longer any legal complications. Expressing optimism, he said State Minister for Housing and Public Works Ahmed Sohel Manzoor had assured them that a new building would be constructed.
Regarding the delay, Tanjila Ferdousi, Executive Engineer of the Health Engineering Department’s Pirojpur Division, said a notice had been served on the contractor. She said the contractor had informed the authorities that, due to illness, he would arrange for his representative to complete the remaining work from the following day and hand over the new building as soon as possible.