Tk 8,626 Crore Mega Project Set for Handover Before Next Monsoon

Chattogram Waterlogging Project Gains Momentum

Work on the waterlogging removal project in Chattogram has gained momentum. The pace of work has been accelerated with the target of completing the entire project by March. The implementing agency, Chattogram Development Authority (CDA), aims to hand over the project to Chattogram City Corporation (CCC) in April, before the next monsoon season.

Those concerned said the project is now almost complete. Although the project deadline has most recently been extended until June 2027, the work will be completed before that date. CDA Chairman Engineer Belayet Hossain said around 98 percent of the waterlogging removal project had been completed. Work has been accelerated with the aim of finishing it before the upcoming month of Ramadan. Waterlogging in the city decreased by 80 to 90 percent during the last monsoon. Once the entire project is completed, the problem of waterlogging in the project area will be permanently resolved.

Under the project, 36 canals are being systematically re-excavated, expanded and developed. These include 16 canals connected to the Karnaphuli River and another 20 canals connected to them. To protect the width of the canals, 85.68 kilometres of roads are being constructed along the banks of important canals. These roads will not only help in cleaning the canals but also play an important role in improving the city’s communication system.

Under the project, 48 pre-stressed concrete (PC) girder bridges and six culverts have been constructed to ensure adequate free-water flow in the canals. In addition, work is underway to construct five tidal regulators, 42 silt traps and three flood retention reservoirs.

Project officials said re-excavation, expansion and renovation work on 30 of the 36 canals had been completed. Work on five other canals was 98 percent complete, with some finishing work still remaining. These activities are ongoing and are expected to be completed by December. Excavation of the Hijra Canal is also underway. The remaining retaining walls, bridges and three silt traps are planned to be completed by March.

Retaining walls have been constructed under the project to prevent the canals from being occupied again. These walls have permanently defined the boundaries of the canals. In addition, service roads have been built alongside the canals to allow modern equipment, such as excavators and dump trucks, to move easily for waste removal and cleaning.

Trees will be planted along these roads to create green spaces where city residents can walk in the afternoon. This will also improve the beauty of the city. Work is now progressing rapidly on the Jamalkhan and Hijra canals. Finishing work is underway on several other canals, while soil is being removed from some sections.

The Army’s 34 Engineer Construction Brigade is implementing the project. If the work is completed by March, the project will be handed over to CCC in April for maintenance. Meanwhile, CCC is also preparing to ensure that the full benefits of the project are maintained. It is also taking initiatives to renovate canals that are not included in the waterlogging removal project.

On August 9, 2017, the Executive Committee of the National Economic Council (ECNEC) approved a CDA project titled ‘Re-excavation, Expansion, Renovation and Development of Canals to Resolve Waterlogging in Chattogram City’ at a cost of Tk 5,616 crore. The three-year project was initially scheduled to be completed by June 2020. According to the latest approved Revised Development Project Proposal (RDPP), the cost of the waterlogging removal project has been increased to Tk 8,626 crore, while its deadline has been extended until June 2027.

To implement the project, the CDA signed a memorandum of understanding (MoU) with the Bangladesh Army on April 9, 2018. Work on the project began on April 28 that year. After facing various complications, the project has now reached its final stage.