Bangladesh Joins the Nuclear Power Club

Bangladesh has entered the era of nuclear power by beginning trial electricity generation at the Rooppur Nuclear Power Plant. On Tuesday, November 17, the country moved closer to fulfilling a long-cherished dream as 350 megawatts of electricity from the plant’s first unit were experimentally connected to the national grid.
The progress of the project is a significant example of Bangladesh’s efforts to maintain its development plans and continuity. The initiative to build the country’s first nuclear power plant dates back to 1961–62, when the then Pakistan government acquired 261 acres of land in Ishwardi, Pabna, to develop a nuclear power project.
Although political instability and the Liberation War halted the initiative, work on the project resumed with renewed momentum in 2010–11 through economic and technological cooperation with Russia. However, allegations of widespread corruption and unusually high costs during the Sheikh Hasina government raised questions about the project. Uncertainty continued until the final days of her administration, with doubts over whether such a sensitive project would eventually be completed under a government seen as operating under India’s influence.
Both the interim government and the BNP government led by Tarique Rahman sought to demonstrate their commitment to completing this major national project, involving an investment of several lakh crore taka. The connection of 350 megawatts of electricity from Rooppur to the national grid on November 17 marked a major milestone in the project’s journey of more than six decades. The start of trial operations has opened a new chapter in Bangladesh’s international standing and development prospects.
A new source of energy amid global uncertainty
Nuclear power plants are operating in 31 countries around the world. Bangladesh has become the 32nd country to join the nuclear power club. This development comes at a time when the war in the Middle East has made the supply of conventional fossil fuels increasingly unstable and uncertain. Electricity shortages have also threatened to disrupt industrial production across the country.
If the trial operations at Rooppur successfully demonstrate the plant’s technological capacity, safety and integrated automated control of electricity supply, the entire project is expected to become commercially operational within a year. The start of trial electricity generation has therefore raised new hopes at a time of energy uncertainty.
Repeated extensions of the project deadline and rising costs, partly attributed to the increase in the value of the US dollar, have made Rooppur one of the world’s most expensive nuclear power projects. The cost of India’s under-construction Kudankulam Nuclear Power Plant Units 3 to 6, with a combined capacity of 4,000 megawatts, is reportedly almost equal to the cost of Bangladesh’s two units at Rooppur. India is also building the Kudankulam units in cooperation with Russia.
The cost per megawatt at the Indian plant is around $3.6 million, while the cost of electricity generation is approximately 5 cents per unit. At Rooppur, the cost per megawatt is around $5.27 million, and the generation cost is approximately 9 cents, or Tk 12, per unit.
Higher expenditure in the power and energy sectors puts additional pressure on the country’s industrial production and commercial competitiveness. However, nuclear power has a much lower risk of environmental pollution from fuel use than conventional fossil fuels. Its ability to generate electricity for long periods using relatively small quantities of fuel also makes it less vulnerable to uncertainties in the supply of gas and furnace oil. Rooppur could also serve as a positive contribution to global efforts to reduce carbon emissions.
Energy security and the challenges ahead
A nuclear power plant that depends on foreign technology and imported raw materials carries several risks. Safety is particularly important for such facilities. With the successful completion of technological synchronisation for safety and operational systems, the Rooppur project has crossed an important stage. As the first unit gradually reaches full capacity and the second unit moves towards commercial operation, Bangladesh’s electricity supply system is set to enter a new era.
The world’s heavy dependence on imported fossil fuels has created serious economic and environmental risks and contributed to global instability. Prime Minister Tarique Rahman is emphasising renewable energy to reduce these risks.
In particular, there is considerable potential to meet electricity demand through solar power by turning its expansion into a socially driven initiative with government support. At the same time, urgent steps are needed to develop the country’s own gas and oil fields and make full use of domestic energy resources.
Dependence on foreign sources in the power and energy sectors puts national security at risk. Bangladesh must move quickly to address the imbalanced arrangements under power projects with India, including the Adani deal. State-owned company Bapex must be strengthened through technological, logistical and investment support so that it can begin exploration and production in the blocks of the Bay of Bengal.
One of the government’s key goals is to overcome challenges in the power and energy sectors and take the country’s commercial and economic potential closer to a trillion-dollar economy. The successful start of trial electricity generation at Rooppur has helped pave the way towards that goal. Ensuring the highest level of safety across all aspects of the nuclear power plant must remain the top priority.